Skip to the content

  • Project: Bundaberg Ring Road - Bridge Deck Units
  • Principal Contractor: Bellero Constructions
  • Deck Weight:
    76 Ton Super T Girders (Walker Street Overpass)
    21 Ton Decks (Clayton Road/Rail Overpass)
  • Cranes Utilised:
    200T Demag (69T counterweight)
    130T Grove (40T counterweight) - Crane by others
    220T Grove (77T counterweight) - Crane by others
  • Project Date: 2009

Description

This project involved the installation of the 2nd and 3rd spans of 76 Ton Super T Girders for the Walker Street Overpass. Due to the length and weight of the decks it was necessary to use two (2) cranes to dual lift the girders into place. Stewart & Sons Steel (operating our 200T Demag) worked in close partnership with Boom Logistics (operating their 220T Grove). Detailed lift studies were prepared to ensure all parties involved were working to the same scope.

The smaller bridge decks for the Clayton Road/Rail Overpass were also installed using our 200 Tonne Demag Hydraulic All Terrain Crane. Installation of one (1) span of decks was performed during a scheduled rail shutdown in the early hours of the morning because of its close proximity to high voltage overhead railway lines.

 

 

Contact Us

(07) 4152 6311

Email Us

 

Find Us

11 Production St,
Svensson Heights
QLD 4670

We specialise in

 

  • Crane Hire
  • Estimating and Tendering
  • Shop Detailing
  • Material Procurement
  • Fabrication
  • Abrasive Blasting and Protective Treatment
  • Delivery
  • Erection and Installation